Calculators / Heap leach facility cost estimator
Free screening calculator — published models

Heap leach facility cost estimator

Enter the ore stacking rate and get an order-of-magnitude capital for a heap leach facility — pad, liners, ponds, stacking and recovery plant (ADR/SX-EW share) — from the published USGS simplified economic filters for open-pit/heap-leach operations (Long & Singer).

t/d ore

How this estimate is computed

Published power-law screening model, evaluated at your capacity:

Capital = 30,000,000 $ × (A / 10,000)0.6   with A = ore stacking rate in t/d ore, valid 2000–60000

Screening is level 1. Negotiation needs level 2.

This free tool runs on published, citable models — order-of-magnitude by design (AACE Class 5). The Costonomics engine adds market-calibrated cost books, OPEX & TCO, and full AACE traceability.